15 Jan 2026
1 min read
15 Jan 2026
Jurisdiction: Victorian Civil and Administrative Tribunal (VCAT), Building and Property List
Members: R Bennett & C Bennett
Hearing Date: 21 July 2025
Decision Date: 23 October 2025
Applicants: Kevin Grech and Jennifer Grech (Grech’s) (represented by Mr J Gray of Just Law, solicitor)
Respondent: Dakota Homes Pty Ltd (Builder) (represented by Mr A Germano of Counsel, instructed by PCL Lawyers)
The Grechs entered into a domestic building contract with the Builder for the construction of a new single-storey dwelling in Wallan, Victoria. The contract was executed on 17 March 2018, with works completed in June 2019. The Grechs alleged defective building work, particularly in relation to the footings and roof, and sought substantial damages, including the cost of rebuilding or rectification. The Builder counterclaimed for the outstanding contract balance ($12,924.30).
The Tribunal, by agreement of the parties, was to identify and make findings as to the following issues ([4], [8]):
The Grechs’ claim was brought under section 8 of the Domestic Building Contracts Act 1995 (Vic) (“DBCA”), alleging breach of the statutory warranties, including that the works would be:
The Grechs bore the onus of proof on the balance of probabilities ([17]). The Tribunal applied established principles regarding damages for breach of contract, including the “ruling principle” that damages should place the claimant in the position they would have been in had the contract been properly performed. [1]
Both parties relied on several findings from each of their appointed experts:
The Tribunal also considered lay evidence from the Grechs and the Builder’s director ([5]-[6]).
The Grechs alleged multiple deficiencies across several amended pleadings, including omitted bored piers, incorrect pier diameters, inadequate founding depths, uncleaned pier holes, inadequate edge beams, and issues with internal footing beams ([27]-[33]).
The Grechs contended that the roof trusses were inadequately supported due to the absence of bored piers under an internal wall ([78]-[79]).
As no breach of statutory warranty was established, the Tribunal found no basis for rectification or damages. The Grechs failed to prove any loss or damage arising from the alleged defects ([75], [77], [84]-[85]).
The Grechs did not contest the Builder’s counterclaim for the outstanding contract balance. The Tribunal ordered payment of $12,924.30 to the Builder ([88]).
This decision reinforces the high evidentiary threshold required to establish defective building work under the DBCA. The Tribunal’s approach underscores:
The case also illustrates the Tribunal’s pragmatic approach to damages, declining to award rectification costs where the evidence does not support the existence of actionable defects or loss, in line with Bellgrove v Eldridge (1954) 90 CLR 613 and Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8.
For assistance with construction disputes and resolving claims for defects contact our building & construction lawyers.
Disclaimer: This article has been prepared for general information purposes and may not apply to your situation. This information should not be relied upon for legal, tax or accounting advice. Your individual circumstances will alter any legal advice given. The views expressed may not reflect the opinions, views or values of PCL Lawyers and belong solely to the author of the content. © PCL Lawyers Pty Ltd.
If you require legal advice specific to your situation please speak to one of our team members today.
As a Partner in PCL Lawyers' Building & Construction team, Emma delivers tailored legal solutions grounded in both technical expertise, solutions focused support and a deep appreciation of her...
You want to know that you are getting advice and real solutions. You not only want a lawyer who has strong experience and knowledge in legal matters, but a lawyer who can also navigate you through the commercial realities.
Request a meeting
"*" indicates required fields